IDR Data
CMS PUF data · 2023 Q1–2025 Q4

CPT 51702: Federal IDR outcomes

Simple insertion of temporary bladder tube

In 2025 Q1–Q4, the provider or facility offer prevailed in 85.9% of 249 determined Federal IDR dispute line items for CPT 51702. The median prevailing offer was 4.34x the QPA (25th–75th percentile 1.76x–8.76x; n = 169). The median time to a decision was 33 business days (n = 249).

Determined line items

249

2025 Q1–Q4 · 0 split decisions excluded

Provider win rate

85.9%

n = 249 · 2025 Q1–Q4

Median payment vs QPA

4.34x

middle half 1.76x–8.76x · n = 169 · 2025 Q1–Q4

Median days to decision

33

business days, from dispute initiation · n = 249 · 2025 Q1–Q4

Dollar amounts

Fewer than 30 line items with dollar amounts in 2025 Q1–Q4; not shown.

Dollar amounts by period

PeriodLine items with $Total awardedTotal QPAAbove QPAMedian awardMedian QPAAward ×QPA ($-weighted)
2025 Q1–Q4Fewer than 30 line items with dollar amounts; not shown.
2024 Q3–Q4Fewer than 30 line items with dollar amounts; not shown.
2024 Q3–2025 Q4Fewer than 30 line items with dollar amounts; not shown.
2023 Q1–2024 Q2Not available (see methodology).

From the CMS QPA and Offers file (see above). Award ×QPA here is total awarded ÷ total QPA, so large claims weigh more than in the per-line median ratio.

By period

PeriodLine itemsWin %Median ×QPA25th–75thRatio nMedian days
2025 Q1–Q424985.9%4.34x1.76x–8.76x16933
2024 Q1–Q45479.6%––2329
2023 Q1–Q4Fewer than 30 determined line items; not shown.
2023 Q1–2025 Q430784.4%4.09x1.58x–8.78x195not pooled

Line items = determined dispute line items (n). Win rate excludes split decisions and includes default decisions. Ratio n = line items reporting a payment-to-QPA ratio. Days are business days as reported by CMS (2023–2024: from IDR entity assignment; 2025: from initiation) and are never pooled.

By state

State (place of service)Line itemsWin %Median ×QPARatio nMedian days
Texas11381.4%6.15x8230
Arizona3193.5%–1529

2025 Q1–Q4 · rows with n ≥ 30 determined line items · sorted by n.

By specialty

Specialty groupLine itemsWin %Median ×QPARatio nMedian days
Emergency medicine and emergency departments14486.1%4.84x12832.5
Hospitals and facilities7290.3%2.56x3538.5

2025 Q1–Q4 · rows with n ≥ 30 determined line items · sorted by n.

Section: Surgery (10004–69990)

FAQ

What is the Federal IDR provider win rate for CPT 51702?

In 2025 Q1–Q4, the provider or facility offer was selected in 85.9% of 249 determined dispute line items for CPT 51702. Split decisions are excluded from the denominator and default decisions are included. Withdrawn, settled and ineligible disputes are not in the CMS data.

How do Federal IDR payments compare with the QPA for CPT 51702?

In 2025 Q1–Q4, the median prevailing offer was 4.34x the qualifying payment amount (QPA), with a 25th to 75th percentile range of 1.76x to 8.76x (n = 169 line items). This uses the CMS field Prevailing Party Offer as % of QPA, where 1.00x equals the QPA.

How long do Federal IDR decisions take for CPT 51702?

In 2025 Q1–Q4, the median was 33 business days (n = 249 line items), using the CMS field Length of Time to Make Determination (from dispute initiation).

How to Utilize IDR